Q: Sixty men can stitch 150 shirts in 30 days working 8 hours a day. In how many days can 35 men stitch 200 shirts working 6 hours a day ?

  • 1
    87.5
  • 2
    89
  • 3
    91.5
  • 4
    93.5
  • Show Answer
  • Workspace

Answer : 3. "91.5"
Explanation :

Answer: C) 91.5 Explanation: We have M1 D1 H1 / W1 = M2 D2 H2 / W2 (Variation rule)(60 x 30 x 8)/ 150 = (35 x D2 x 6) / 200 D2 = (60 x 30 x 8 x 200) / (150 x 35 x 6) => D2 = 91.42 days =~ 91.5 days.