The efficiency of L is 25% more than P. L started a work alone and then P joined her 5 days before actual completion of the work. For how many days L worked alone?
5 841 5ea9405b07542b13ae2c1662
Q:
The efficiency of L is 25% more than P. L started a work alone and then P joined her 5 days before actual completion of the work. For how many days L worked alone?
- 19false
- 211true
- 310false
- 425false
- 512false
- Show Answer
- Workspace
- Discuss