To do a certain work, the ratio of the efficiencies of A and B is 7: 5. Working together, they can complete the same work in $$17{1\over 2}$$ days. A alone will complete 60% of the same work in:
5 322 64c7641f3fde307e3f4a8bb1
Q:
To do a certain work, the ratio of the efficiencies of A and B is 7: 5. Working together, they can complete the same work in $$17{1\over 2}$$ days. A alone will complete 60% of the same work in:
- 118 daystrue
- 215 daysfalse
- 316 daysfalse
- 421 daysfalse
- Show Answer
- Workspace
- Discuss