X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?5
1723 5b5cc6bfe4d2b4197774da0a
Q: X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?
- 11/3false
- 22/3false
- 31/6true
- 45/6false
- Show Answer
- Workspace
- Discuss