X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in :
5 1058 600828a5da57152562a6db09
Q:
X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in :
- 127 daysfalse
- 236 daystrue
- 342 daysfalse
- 418 daysfalse