Q.1. If m men can do a work in r days, then the number of days taken by (m+n) men to do it is
(A) (m+n)/mn
(B) (m+n)/mr
(C) mr/(m+n)
(D) (m+n)r/mn
Q.2. A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?
(A) 6
(B) 4
(C) 5
(D) 10
Q.3. Tap A fills a tank in 10 h and tap B can fill it in 15 h. Both are opened simultaneously. Sometimes later tap B was closed, then it takes total 8 h to fill up the whole tank. After how many hours tap B was closed?
(A) 2
(B) 3
(C) 4
(D) 5
Q.4. Alen and Border can do a work individually in 21 days and 42 days, respectively. In how many days they can complete the work, working alternatively?
(A) 14
(B) 28
(C) 42
(D) 35
Q.5. A takes 6 days less than B to do a certain job and 2 days more than C. A and B together can do the work in the same time as C. In how many days B alone can do the complete work?
(A) 10
(B) 14
(C) 12
(D) 16
Ask me in the comment section, if you face any problem while solving important Time and Work questions. Visit next page for more Time and Work problems.