Q :  

Manu works 3 times as fast as Raju. If Raju can complete a job alone in 60 days, then in how many days can they together finish the job?

(A) 7 days

(B) 4 days

(C) 5 days

(D) 15 days

Correct Answer : D

Q :  

If 20 women can lay a road of length 100m in 10 days. 10 women can lay the same road of length 50m in: 

(A) 10 day

(B) 20 day

(C) 5 day

(D) 15 day

Correct Answer : A

Q :  

A wall of 100 metres can be built by 7 men or 10 women in 10 days. How many days will 14 men and 20 women take to build a wall of 600 metres 

(A) 25

(B) 30

(C) 15

(D) 20

Correct Answer : C

Q :  

8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed? 

(A) 4 days

(B) 5 days

(C) 2 days

(D) 3 days

Correct Answer : A

Q :  

A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is?

(A) 16 days

(B) 10 days

(C) 12 days

(D) 15 days

Correct Answer : D

If you want to practice more questions related to Time and work then you can go to the link provided below.

https://www.examsbook.com/time-and-work-formulas-with-examples-for-ssc-and-bank-exams

In this post I have made every effort to explain the Time and work in a simple way, even if you are having problems in any manner or question, you can Ask me by writing in the comment box below.

Related categories

Very important related articles. Read now

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today