Maths Questions Series #5

Vikram Singh2 years ago 37.4K Views Join Examsbookapp store google play
maths questions series

Very important Maths questions for SSC CGL


Q. The east positive integer that should be subtracted from 3011 * 3012 so that the difference is perfect square is-

a. 3009
b. 3010
c. 3011
d. 3012



Q. P, Q, R are employed to do a work for Rs. 5750. P and Q together finished 19/23 of work and Q and R together finished 8/23 of work. Wage of Q, in rupees, is-

a. 2850
b. 3750
c. 2750
d. 1000



Q. A can do a piece of work in 24 day, B in 32 days and C in 64 days. All begin to do it together, but A leaves after 6 days and B leaves 6 days before the completion of the work. How many days did the work last?

a. 15
b. 20
c. 18
d. 30






Q. The square root of (0.75)3 /1-0.75 + [0.75 + 90.75)2 +1] is-

a. 1
b. 2
c. 3
d. 4




Q. Given that ?4096 = 64, the value of ?4096 + ?40.96 +?0.004096 is-

a. 70.4
b. 70.464
c. 71.104
d. 71.4




Q. By selling an article at 3/4th of the marked price, there is a gain of 25%. The ratio of the marked price and the cost price is-

a. 5 : 3
b. 3 : 5
c. 3 : 4
d. 4 : 3




Q. A and B earn in the ratio 2:1. They spend in the ratio 5:3 and save in the ratio 4:1. If the total monthly savings of both A and B are Rs.5,000, the monthly income of B is-

a. Rs.7,000
b. Rs.14,000
c. Rs.5,000
d. Rs.10,000




Q. The ratio of the sum of two numbers and their difference is 5:1. The ratio of the greater number to the smaller number is-

a. 2 : 3
b. 3 : 2
c. 5 : 1
d. 1 : 5




Q. A cistern has 3 pipes A, B and C. A and B can fill it in 3 and 4 hours respectively, and C can empty it in 1 hour. If the pipes are opened at 3 p.m., 4 p.m. and 5 p.m. respectively on the same day, the cistern will be empty at-
a. 7.12 p.m.
b. 7.15 p.m.
c. 7.10 p.m.
d. 7.18 p.m.




Q. If A works alone, he would take 4 days more to complete the job than if both A and B worked together. If B worked alone, he would take 16 days more to complete the job than if A and B work together. How many days would they take to complete the work if both of them worked together?

a. 10 days
b. 12 days
c. 6 days
d. 8 days


Showing page 2 of 11

    Choose from these tabs.

    You may also like

    About author

    Vikram Singh

    Providing knowledgable questions of Reasoning and Aptitude for the competitive exams.

    Read more articles

      Report Error: Maths Questions Series #5

    Please Enter Message
    Error Reported Successfully