Join Examsbook
875 0

Q:

15 person can complete a work in 60 days. If the number of persons is increased by 5, how many days earlier will the work get completed?

  • 1
    45 days
  • 2
    10 days
  • 3
    20 days
  • 4
    15 days
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "15 days"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully