30 Men contracts to complete a work in 50 days. But after 25 days, it is come to know that only 1/3rd of the work has been done. How many more workers are required to complete the work in time?5
Q: 30 Men contracts to complete a work in 50 days. But after 25 days, it is come to know that only 1/3rd of the work has been done. How many more workers are required to complete the work in time?
- 125false
- 230true
- 335false
- 440false
- Show AnswerHide Answer
- Workspace