Q: 45 men can complete a work in 16 days, 6 days after they started working. 30 more men join them. How many days will they now take to complete the remaining work?

  • 1
    4
  • 2
    5
  • 3
    6
  • 4
    8
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "6"
Explanation :

Total work M1D1= M2D2 ⇒(45✖16-45✖6)=75✖D⇒D2=6 days