45 men working 9 hours per day dig 40 m deep. How many extra men should be put to dig to a depth of 56 m working 7 hours per day ?5
Q: 45 men working 9 hours per day dig 40 m deep. How many extra men should be put to dig to a depth of 56 m working 7 hours per day ?
- 136true
- 261false
- 348false
- 454false
- Show AnswerHide Answer
- Workspace
Answer : 1. "36"
Explanation :
Answer: A) 36 Explanation: (45 x 9)/40 = (M x 7)/56 => M = 81 => 81 – 45 = 36