9 men and 12 boys finish a job in 12 days, 12 men and 12 boys finish it in 10 days. 10 men and 10 boys shall finish it in how many days ?5
Q: 9 men and 12 boys finish a job in 12 days, 12 men and 12 boys finish it in 10 days. 10 men and 10 boys shall finish it in how many days ?
- 115 daysfalse
- 211 daysfalse
- 314 daysfalse
- 412 daystrue
- Show AnswerHide Answer
- Workspace
Answer : 4. "12 days"
Explanation :
Answer: D) 12 days Explanation: 9M + 12B ----- 12 days ...........(1)12M + 12B ------- 10 days........(2)10M + 10B -------?108M + 144B = 120M +120B24B = 12M => 1M = 2B............(3) From (1) & (3) 18B + 12B = 30B ---- 12 days 20B + 10B = 30B -----? => 12 days.