Join Examsbook
823 0

Q:

A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in 

  • 1
    5 days
  • 2
    $$ 5{1\over3}$$ days
  • 3
    8 days
  • 4
    10 days
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "$$ 5{1\over3}$$ days"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully