A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves , B continues for 2 more days , and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work? 

  • 1
    5 days
  • 2
    8 days
  • 3
    3 days
  • 4
    4 days
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "4 days "