Join Examsbook
869 0

Q:

A and B together can complete a work in 21 days. If A takes 42 days to complete the work alone, how many days will B take to complete the same work alone?

  • 1
    32
  • 2
    42
  • 3
    27
  • 4
    36
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "42"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully