A can complete a piece of work in 12 days, A, B and C can complete the work in 6 days. Efficiency of B is 0.5 times the efficiency of A. In how many days C can complete the work alone?
5Q:
A can complete a piece of work in 12 days, A, B and C can complete the work in 6 days. Efficiency of B is 0.5 times the efficiency of A. In how many days C can complete the work alone?
- 110 daysfalse
- 216 daysfalse
- 324 daystrue
- 412 daysfalse
- 5None of thesefalse
- Show AnswerHide Answer
- Workspace