Join Examsbook
583 0

Q:

A can do a piece of work in 18 days and B in 36 days. If they work together for 9 days, then what percentage of work will be left?

  • 1
    33.3
  • 2
    20
  • 3
    25
  • 4
    36
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "25"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully