Join Examsbook
2645 0

Q: A certain work can be completed in 100 days by a certain number of men. But, due to the absence of 10 people it could be completed in 110 days. How many workers were employed initially?

  • 1
    100
  • 2
    110
  • 3
    55
  • 4
    50
  • Show AnswerHide Answer
  • Workspace

Answer : 2. " 110"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully