Join Examsbook
A contract is to be completed in 50 days and 105 men were set to work, each working 8 hour a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 hour a day?
5Q:
A contract is to be completed in 50 days and 105 men were set to work, each working 8 hour a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 hour a day?
- 134false
- 236false
- 335true
- 437false
- Show AnswerHide Answer
- Workspace