Join Examsbook
2212 0

Q: A contractor undertook to complete a piece of work in 120 Days and employed 140 men upon it. At the end of 66 days only half of the work was done,so he put on 25 extra men. By how much time did he exceed the specific time ?

  • 1
    2 days
  • 2
    3 days
  • 3
    4 days
  • 4
    5 days
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "2 days"
Explanation :

Answer: A) 2 days Explanation: work done=total number of person x number of days;half of work done = 140 x 66;For half of remaining work 25 extra men are added.Therefore, total men for half work remaining = 140 + 25 = 165;Let 2nd half work will be completed in K days;140 x 66 = 165 x KK = 122;Hence, extra days => 122-120 = 2days.

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully