Join Examsbook
746 0

Q:

A does 2/5 of a work in 9 days. Then B joined him and they together completed the remaining work in 6 days. B alone can finish the whole work in

  • 1
    12/13 days
  • 2
    2/11 days
  • 3
    10 days
  • 4
    18 days
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "18 days"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully