A skilled, a half skilled and an unskilled labourer work for 7, 8 and 10 days respectively and they together get ₹ 369 for their work. If the ratio of their each day’s work is $${1\over3}$$: $${1\over4}$$: $${1\over6}$$, then how much does the trained labourer get (in rupees) ?
5Q:
A skilled, a half skilled and an unskilled labourer work for 7, 8 and 10 days respectively and they together get ₹ 369 for their work. If the ratio of their each day’s work is $${1\over3}$$: $${1\over4}$$: $${1\over6}$$, then how much does the trained labourer get (in rupees) ?
- 1201.50false
- 2143.50true
- 3164false
- 4102.50false
- Show AnswerHide Answer