Ajay. Vijay and Sashi can do a piece of work in 20, 40 and 60 days, respectively. In how many days can Ajay do the work if he is assisted by Vijay and Sashi on every fourth day?

  • 1
    15 days
  • 2
    $${{150\over3}}$$ days
  • 3
    12 days
  • 4
    $${{44\over3}}$$ days
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "$${{150\over3}}$$ days"