Aman and Raman together can complete a work in 30 days, Raman and Manan can complete the same work in 36 days and Manan and Aman can complete the same work in 45 days. In how many days can all three together complete the work?
5Q:
Aman and Raman together can complete a work in 30 days, Raman and Manan can complete the same work in 36 days and Manan and Aman can complete the same work in 45 days. In how many days can all three together complete the work?
- 112false
- 232false
- 324true
- 455false
- Show AnswerHide Answer