Join Examsbook
1903 0

Q:

Anil, Deepak, and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?

  • 1
    105 days
  • 2
    84 days
  • 3
    96 days
  • 4
    110 days
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "84 days"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully