Join Examsbook
607 0

Direction: Study the following information carefully and answer the given questions.
Data below represent number of people required for various project to be completed in various days:

Q:

If 0.5 Y people work on project B for 10 days and then 0.5Y people join the project after 10 days. How many days will it take to complete the Project B?

  • 1
    35 days
  • 2
    40 days
  • 3
    45 days
  • 4
    50 days
  • 5
    None of these
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "40 days"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully