If 0.5Y people work on Project B for 10 days and then 0.5Y more people joined the project, then how many days will it take to complete the Project B?
5Directions: Given information represents number of people required for three different projects to be completed in various days.
Q:
If 0.5Y people work on Project B for 10 days and then 0.5Y more people joined the project, then how many days will it take to complete the Project B?
- 135 daysfalse
- 240 daystrue
- 345 daysfalse
- 450 daysfalse
- 5None of thesefalse
- Show AnswerHide Answer
- Workspace