If 10 men take 15 days to complete a work. In how many days will 37 men complete the work?5
Q: If 10 men take 15 days to complete a work. In how many days will 37 men complete the work?
- 13 daysfalse
- 24 daystrue
- 35 daysfalse
- 46 daysfalse
- Show AnswerHide Answer
- Workspace
Answer : 2. "4 days"
Explanation :
Answer: B) 4 days Explanation: Given 10 men take 15 days to complete a work => Total mandays = 15 x 10 = 150 Let the work be 150 mandays. => Now 37 men can do 150 mandays in 150/37 =~ 4 days