If 18 men can finish a job in 26 days, then, in how many days will 13 men finish the same job?
5Q:
If 18 men can finish a job in 26 days, then, in how many days will 13 men finish the same job?
- 122 daysfalse
- 236 daystrue
- 325 daysfalse
- 419 daysfalse
- Show AnswerHide Answer