Join Examsbook
2656 0

Q: If 34 men completed 2/5th of a work in 8 days working 9 hours a day. How many more man should be engaged to finish the rest of the work in 6 days working 9 hours a day ?

  • 1
    101 men
  • 2
    112 men
  • 3
    102 men
  • 4
    120 men
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "102 men"
Explanation :

Answer: C) 102 men Explanation: From the above formula i.e (m1 x t1/w1) = (m2 x t2/w2) so, [(34 x 8 x 9)/(2/5)] = [(M x 6 x 9)/(3/5)] so, M = 136 men   Number of men to be added to finish the work = 136-34 = 102 men.

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully