P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ?5
Q: P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ?
- 156 daysfalse
- 254 daysfalse
- 360 daysfalse
- 464 daystrue
- Show AnswerHide Answer
- Workspace
Answer : 4. "64 days"
Explanation :
Answer: D) 64 days Explanation: (P+Q)'s 1 day work = 1/24 P's 1 day work = 1/32 => Q's 1 day work = 1/24 - 1/32 = 1/96 Work done by (P+Q) in 8 days = 8/24 = 1/3 Remainining work = 1 - 1/3 = 2/3 Time taken by Q to complete the remaining work = 2/3 x 96 = 64 days.