P takes 5 more hours to complete a work in comparison to Q. They work together for 6 hours. In how many days can Q complete the same work.5
Q: P takes 5 more hours to complete a work in comparison to Q. They work together for 6 hours. In how many days can Q complete the same work.
- 18 hoursfalse
- 210 hoursfalse
- 312 hoursfalse
- 415 hourstrue