Priya can do a work in 16 days. In how many days will the work be completed by Sai, if the efficiency of Sai is 60% more than that of Priya ?5
Q: Priya can do a work in 16 days. In how many days will the work be completed by Sai, if the efficiency of Sai is 60% more than that of Priya ?
- 18 daysfalse
- 212 daysfalse
- 314 daysfalse
- 410 daystrue
- Show AnswerHide Answer
- Workspace
Answer : 4. "10 days"
Explanation :
Answer: D) 10 days Explanation: Ratio of efficiencies of Priya and Sai is Sai : Priya = 160 : 100 = 8 : 5 Given Priya completes the work in 16 days Let number of days Sai completes the work be 'd' => 5×16 = 8×d d = 10 days. Therefore, number of days Sai completes the work is 10 days.