Join Examsbook
676 0

Q: Project Integration Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Integrated Change Control Phase?

  • Show AnswerHide Answer
  • Workspace

Answer :
Explanation :

I. Inputs Project management plan Requested changes Work performance information Recommended preventive actions Recommended corrective actions Recommended defect repair Deliverables II. Tools and Techniques Project management methodology Project management information system Expert Judgment III. Outputs Approved change requests Rejected change requests Project management plan(updates) Project scope statement (updates) Approved corrective actions Approved preventive actions Approved defect repair Validated defect repair Deliverables

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully