Raghu can complete a work in 12days working 9 hours a day. Arun can complete the same work in 8 days working 11 hours a day. If both Raghu and Arun work together, working 12 hours a day, in how many days can they complete the work ?5
Q: Raghu can complete a work in 12days working 9 hours a day. Arun can complete the same work in 8 days working 11 hours a day. If both Raghu and Arun work together, working 12 hours a day, in how many days can they complete the work ?
- 13449 daysfalse
- 212449 daysfalse
- 34349 daystrue
- 441249 daysfalse
- Show AnswerHide Answer
- Workspace
Answer : 3. "4349 days"
Explanation :
Answer: C) Option C Explanation: Raghu can complete the work in (12 x 9)hrs = 108 hrs. Arun can complete the work in (8 x 11)hrs = 88 hrs. Raghu's 1 hrs work = 1/108 and Arun's 1 hrs work = 1/88 (Raghu + Arun)'s 1 hrs work = 1108+188=492376 So, both Raghu and Arun will finish the work in 237649 hrs Number of days of 12 hours each=237649×112 = 19849=4349 days