Ramesh can do a work in 21 days and Mahesh in 42 days. If they work on it together for 7 days, then what fraction of work is left?

  • 1
    $$ {1\over5}$$
  • 2
    $$ {1\over4}$$
  • 3
    $$ {1\over2}$$
  • 4
    $$ {2\over3}$$
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "$$ {1\over2}$$"