Q:

Two men can complete a work in 9 days. How many men will be required to complete twice the work in 12 days?

  • 1
    2
  • 2
    3
  • 3
    11
  • 4
    4
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "3"