Q: Your company has a policy of having every software project reviewed and approved by the Architecture Review Board prior to the construction phase of a project. you are currently in the process of activity sequencing. This is a example of what?
- 1Gatekeepingfalse
- 2Milestonetrue
- 3New scope for the projectfalse
- 4Project integrationfalse
- Show AnswerHide Answer
- Workspace
Answer : 2. "Milestone"
Explanation :
Answer: B) Milestone Explanation: The approval by the Architecture Review Board is a milestone you want to include in activity sequencing so that you can ensure the requirements for meeting the review board's approval are met. Answer A is tempting because the question references phase-end activities; however, it is not an example of gatekeeping because the project is not being authorized to continue based only on the architecture review.Gatekeeping often involves the review of other factors as well. Answer C is incorect because the requirement of a review board approval does not afect scope. Answer D is incorrect because project integration planning involves project plan development, execution, and integrated change control, which are not related to a review board.