Time and Work Short Tricks Solved Problems for Competitive Exams
Time and Work Short Tricks Solved Problems
Example 5: 16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days.
(A) 10
(B) 8
(C) 16
(D) 32
Solution
M × D = W,
16 × 6 = 1/3 W
Rest work = 2/3 W
For double work in same time 32 men are required to do the work or 16 more men required to do the work.
Shor trick
2×(16×6) = 6×M → M = 32.
⸫ 16 more men are required.
Example 6: A group of men decided to do a job in 4 days. But since 20 men dropped out every day, the job completed the at the end of the 7th day. How many men were there at the beginning?
(A) 240
(B) 140
(C) 280
(D) 150
Let n be the initial number of men, then n × 4 = n +(n-20)+(n-40)+…….+(n-120)
→ 4n = 7n – 240 → 3n = 420
⸫ n = 140 men.
Short Tricks
Go through option
140 × 4 = ( 140 + 120 +100+….+20)
560 = 560
Example 7: A is twice as good a workman as B and therefore A takes 6 days less than B to finish the work individually. If A and B working together complete the work in 4 days, then how many days are required by B to complete the work alone?
(A) 12
(B) 18
(C) 8
(D) 6
Solution
A B
Efficiency → 2 : 1
Days → 1 : 2
{Days α 1/Efficiency}
Now, let A requires X days, then B requires 2X days
⸫ Difference in number of days
{=(2X – X) = X = 6 → X = 6
⸫ B requires 2X = 2×6 = 12 days.
Second Method:
If A takes X days, then B takes ( X+6) days.
Now, A’s 1 day’s work = 1/X.
B’s 1 day’s work = 1/(X+6) ⸫ (1/X)/1/(X+6) = 2/1.
(Since, A does twice the work as B does)
→ X = 6
⸫ B takes 2x = 12 days.
Third Method:
(1/X) + {1/(X+6)} = 1/4.
→ X = 6 and 2X = 12 days (required by B).
Visit on the next page for more practice of these questions. You can ask me anything in the comment section about this topic.