Get Started
904

Q: The project life cycle can be broken into five phases that tend to overlap with each other frm one phase to another;however ,the control phase does not overlap with a specific phase. why?

  • 1
    Change control management is seperate from the other phases
  • 2
    Change control management has a plan that can be usede throughout the initiation, planning, execution, and closeout of the project
  • 3
    Because the project sponsor is responsible for change control management , the project manager is not involved with that phase of the project
  • 4
    Change control extends throughout the entire project from initiation to closeout
  • Show Answer
  • Workspace

Answer : 4. "Change control extends throughout the entire project from initiation to closeout"
Explanation :

Answer: D) Change control extends throughout the entire project from initiation to closeout Explanation: Change control management is utilized from the begining to the end of the project in order to keep it focused with an emphasis on the time and budget. Answer A is incorrect because change control management is not seperate from the other phases. Answer B is incorrect because the control plan must be throughout the other phases of a project. Its usage is not optional, and consistent utilization is imperative to managing scope creep and other scope expansions. Answer C is incorrect because the project sponsors is generally not responsible for the change control documentation, although it should be involved in the buy-in and approval process.

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today