Time and Work Problems and Solutions

Q :  

A's 2 days work is equal to B's 3  days work. If A can complete the work in 8 days, then to complete the work B will take: 

(A) 16 days

(B) 14 days

(C) 15 days

(D) 12 days

Correct Answer : D