Q: Ram and Naresh can complete a work in 20 days while Naresh takes 36 days. They get Rs 720 for it. Find salary of Ram. 3762 2

  • 1
    Rs 300
    Correct
    Wrong
  • 2
    Rs 380
    Correct
    Wrong
  • 3
    Rs 400
    Correct
    Wrong
  • 4
    Rs 320
    Correct
    Wrong
  • Show Answer
  • Workspace

Answer : 4. "Rs 320"

Q: 26 men can complete a piece of work in 17 days. How many more men must be hired to complete the work in 13 days? 2634 1

  • 1
    9
    Correct
    Wrong
  • 2
    8
    Correct
    Wrong
  • 3
    6
    Correct
    Wrong
  • 4
    18
    Correct
    Wrong
  • Show Answer
  • Workspace

Answer : 2. "8"

Q:

Directions : What should come in place of the question mark (?) in the following number series? 

87 89 95 107 ? 157 

2278 0

  • 1
    127
    Correct
    Wrong
  • 2
    122
    Correct
    Wrong
  • 3
    139
    Correct
    Wrong
  • 4
    140
    Correct
    Wrong
  • 5
    None of these
    Correct
    Wrong
  • Show Answer
  • Workspace

Answer : 1. "127 "

Q: A and B together can complete a work in 10 days. A alone can do it in 40 days. In how many days B alone can complete it? 3467 4

  • 1
    Correct
    Wrong
  • 2
    10
    Correct
    Wrong
  • 3
    8
    Correct
    Wrong
  • 4
    30/7
    Correct
    Wrong
  • Show Answer
  • Workspace

Answer : 1. ""

Q: Ram can complete ¼ th part of work in 8 days and Shyam can complete 2/4 th of the work in 6 days and Naresh can complete ¾th the work in 12 days. In how many days can they together complete it? 2788 1

  • 1
    Correct
    Wrong
  • 2
    Correct
    Wrong
  • 3
    Correct
    Wrong
  • 4
    Correct
    Wrong
  • Show Answer
  • Workspace

Answer : 2. ""

Q: A complete a work at four times the speed than C. If together they can complete a work in 20 days, in how many days can A alone complete it? 3356 0

  • 1
    25
    Correct
    Wrong
  • 2
    100
    Correct
    Wrong
  • 3
    75
    Correct
    Wrong
  • 4
    80
    Correct
    Wrong
  • Show Answer
  • Workspace

Answer : 1. "25"

Q: 30 Men can complete a work in 25 days. In how many days can 75 men complete it? 4616 2

  • 1
    15
    Correct
    Wrong
  • 2
    12
    Correct
    Wrong
  • 3
    16
    Correct
    Wrong
  • 4
    10
    Correct
    Wrong
  • Show Answer
  • Workspace

Answer : 4. "10"

Q:

Directions : What should come in place of the question mark (?) in the following number series? 

474 459 429 369 249 ?

1580 0

  • 1
    9
    Correct
    Wrong
  • 2
    0
    Correct
    Wrong
  • 3
    4
    Correct
    Wrong
  • 4
    11
    Correct
    Wrong
  • 5
    None of these
    Correct
    Wrong
  • Show Answer
  • Workspace

Answer : 1. "9"

  Report Error

Please Enter Message
Error Reported Successfully

  Report Error

Please Enter Message
Error Reported Successfully

  Report Error

Please Enter Message
Error Reported Successfully

  Report Error

Please Enter Message
Error Reported Successfully

  Report Error

Please Enter Message
Error Reported Successfully

  Report Error

Please Enter Message
Error Reported Successfully

  Report Error

Please Enter Message
Error Reported Successfully

  Report Error

Please Enter Message
Error Reported Successfully