Time and Work Questions Practice Question and Answer

Q: A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In how many days all three together can do the work ? 1298 0

  • 1
    80 days
    Correct
    Wrong
  • 2
    100 days
    Correct
    Wrong
  • 3
    60 days
    Correct
    Wrong
  • 4
    150 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. " 60 days"

Q:

A is as efficient as B and C together. Working together A and B can complete a work in 36 days and C alone can complete it in 60 days. A and C work together for 10 days. B alone will complete the remaining work in:

462 0

  • 1
    88 days
    Correct
    Wrong
  • 2
    110 days
    Correct
    Wrong
  • 3
    84 days
    Correct
    Wrong
  • 4
    90 days
    Correct
    Wrong
  • 5
    40 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "110 days"

Q:

A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?

455 0

  • 1
    60 days
    Correct
    Wrong
  • 2
    72 days
    Correct
    Wrong
  • 3
    54 days
    Correct
    Wrong
  • 4
    64 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "72 days"
Explanation :

Let's denote the work rate of A as "A" and the work rate of B as "B." We know that A is three times as efficient as B, so we can write:

A = 3B

Now, we also know that A and B can do a work together in 18 days. The work rate of A and B combined is the sum of their individual work rates, which can be represented as:

A + B

Since they complete the work in 18 days together, we can write:

(A + B) = 1/18

Now, we want to find how long it would take B alone to complete the work. Let's denote that time as "x" days. The work rate of B alone would be:

B (work rate of B alone) = 1/x

Now, we have two equations:

A = 3B

(A + B) = 1/18

We can substitute the value of A from the first equation into the second equation:

(3B + B) = 1/18

Combine like terms:

4B = 1/18

Now, isolate B by dividing both sides by 4:

B = (1/18) / 4

B = 1/72

So, B's work rate is 1/72 of the work per day. To find how many days B alone can complete the work, take the reciprocal of B's work rate:

x (number of days for B alone) = 1 / (1/72)

x = 72

Therefore, it would take B alone 72 days to complete the work.

Q:

A alone can do a piece of work in 15 days, while B alone can do it in 20 days. They work together for 6 days and the rest of the work is done by C in 6 days. If they get Rs 800 for the whole work, how should they divide the money?

515 0

  • 1
    Rs. 320, Rs. 240 and Rs. 240
    Correct
    Wrong
  • 2
    Rs. 640, Rs. 280 and Rs. 260
    Correct
    Wrong
  • 3
    Rs. 320, Rs. 420 and Rs. 360
    Correct
    Wrong
  • 4
    Rs. 360, Rs. 420 and Rs. 240
    Correct
    Wrong
  • 5
    Rs. 320, Rs. 240 and Rs. 720
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "Rs. 320, Rs. 240 and Rs. 240"
Explanation :

Let's break down the problem step by step:

  1. A can complete the work in 15 days, so his daily work rate is 1/15 of the work per day.
  2. B can complete the work in 20 days, so his daily work rate is 1/20 of the work per day.
  3. A and B work together for 6 days. In these 6 days, their combined work rate is (1/15 + 1/20) = (4/60 + 3/60) = 7/60 of the work per day.
  4. In 6 days, they complete (6 * 7/60) = 42/60 of the work, which simplifies to 7/10 of the work.

Now, let C complete the remaining 3/10 of the work in 6 days. We can calculate C's daily work rate:

C's daily work rate = Work done by C in 6 days / 6 C's daily work rate = (3/10) / 6 C's daily work rate = 1/20 of the work per day.

Now, let's calculate the total amount earned by each worker:

  1. A's share: A worked for 6 days at a rate of 1/15 of the work per day, so he completed (6 * 1/15) = 2/5 of the work. A's share of the money is (2/5) * Rs 800 = Rs 320.

  2. B's share: B worked for 6 days at a rate of 1/20 of the work per day, so he completed (6 * 1/20) = 3/10 of the work. B's share of the money is (3/10) * Rs 800 = Rs 240.

  3. C's share: C worked for 6 days at a rate of 1/20 of the work per day, so he completed (6 * 1/20) = 3/10 of the work. C's share of the money is (3/10) * Rs 800 = Rs 240.

Now, to check if the total amount is correct, you can add up their individual shares:

Rs 320 (A) + Rs 240 (B) + Rs 240 (C) = Rs 800

So, they should divide the money as follows:

  • A gets Rs 320.
  • B gets Rs 240.
  • C gets Rs 240.

Q:

A, B and C can complete a work in 10, 20 and 30 days respectively. If D can destroy the same work in 15 days. Find the time taken by all of them to complete the whole work.

602 0

  • 1
    50/7days
    Correct
    Wrong
  • 2
    60/7 days
    Correct
    Wrong
  • 3
    20/3 days
    Correct
    Wrong
  • 4
    40/7 days
    Correct
    Wrong
  • 5
    None of these
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "60/7 days"

Q:

A and B together can do a piece of work in 12 days, A and C together can do the same work in 15 days. If B and C together can do the same work in 20 days, then in how many days A, B and C together can complete the same work?

423 0

  • 1
    8
    Correct
    Wrong
  • 2
    6
    Correct
    Wrong
  • 3
    10
    Correct
    Wrong
  • 4
    9
    Correct
    Wrong
  • 5
    None of these
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "10"

Q:

P can do a task in 30 days, Q is 50% more efficient than P, R can do the same work in 10 days less than Q if R and Q start task together and after X days they left the task and P completed the remaining task in (X + 8) days. then find the value of X?

604 0

  • 1
    2
    Correct
    Wrong
  • 2
    4
    Correct
    Wrong
  • 3
    5
    Correct
    Wrong
  • 4
    8
    Correct
    Wrong
  • 5
    6
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "4"

Q:

A alone can complete a work in 25 days and B alone can do the same work in 20 days. A started the work and after working 7 days B joined A to finish the remaining work. In how many days, the total work will be finished?

424 0

  • 1
    8 days
    Correct
    Wrong
  • 2
    15 days
    Correct
    Wrong
  • 3
    9 days
    Correct
    Wrong
  • 4
    12 days
    Correct
    Wrong
  • 5
    None of these
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "15 days"

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully