Time and Work Questions Practice Question and Answer

  • Show AnswerHide Answer
  • Workspace

Answer : 3. "25"

Q:

36 people working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days. If they work for 6 hours a day?

974 1

  • 1
    50
    Correct
    Wrong
  • 2
    55
    Correct
    Wrong
  • 3
    60
    Correct
    Wrong
  • 4
    45
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "60"

Q:

The ratio of the efficiencies of A. B and C is 7: 5: 4. Working together, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone:

933 0

  • 1
    60
    Correct
    Wrong
  • 2
    63
    Correct
    Wrong
  • 3
    56
    Correct
    Wrong
  • 4
    49
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "56"

Q:

A and B together can complete a work in 12 days, A alone can complete in 20 days. If B now does the work only for half a day daily, then the number of days required to complete the work, by A and B together, is

778 0

  • 1
    18
    Correct
    Wrong
  • 2
    15
    Correct
    Wrong
  • 3
    14
    Correct
    Wrong
  • 4
    16
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "15"

Q:

A can finish work in 18 days and B in 36 days. If they work on it together for 9 days, what percent of work is left?

803 0

  • 1
    33.33
    Correct
    Wrong
  • 2
    20
    Correct
    Wrong
  • 3
    75
    Correct
    Wrong
  • 4
    25
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "25"

Q:

If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day?

925 0

  • 1
    18 days
    Correct
    Wrong
  • 2
    16 days
    Correct
    Wrong
  • 3
    20 days
    Correct
    Wrong
  • 4
    15 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "16 days"

Q: A, B and C together can do a work in 8 days if A and B can do it in 20 and 30 days respectively. In how many days C alone can complete it? 3608 2

  • 1
    16
    Correct
    Wrong
  • 2
    18
    Correct
    Wrong
  • 3
    20
    Correct
    Wrong
  • 4
    24
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "24"

Q:

Two men can complete a work in 9 days. How many men will be required to complete twice the work in 12 days?

750 0

  • 1
    2
    Correct
    Wrong
  • 2
    3
    Correct
    Wrong
  • 3
    11
    Correct
    Wrong
  • 4
    4
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "3"

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully