Time and Work Questions Practice Question and Answer
8 Q: S1 can do a piece of work alone in 9 days, S2 can do the same work alone in 18 days, while S3 can do it alone in 27 days. They work together and complete the work, and receive a total of ₹ 726 as payment for doing the work. What is the combined share of S2 and S3, taken together from the above amount?
1006 064225391b34a0b67fc0b1444
64225391b34a0b67fc0b1444- 1₹ 270false
- 2₹ 300false
- 3₹ 330true
- 4₹ 360false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "₹ 330"
Q: A and B together can complete a piece of work in 3 days. They start together. But, after 2 days, B left the work, if the work is completed after 2 next days. B alone could do the work in
854 060057dc0d517b811ff7934f6
60057dc0d517b811ff7934f6- 110 daysfalse
- 24 daysfalse
- 36 daystrue
- 48 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "6 days"
Q: A work could be completed in 100 days by some workers. How- ever, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
436 06401e2ea86fd4161466d6a1c
6401e2ea86fd4161466d6a1c- 1100false
- 2110true
- 3180false
- 4144false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "110"
Q: A can finish a piece of work in 18 days and B can do the same work in half the time taken by A. Then working together. What part of the same work they an finish in a day? 1104 05cf0f058c97a225730e3b24b
5cf0f058c97a225730e3b24b- 1$${1\over 6}$$true
- 2$${2\over 5}$$false
- 3$${1\over 9}$$false
- 4$${2\over 7}$$false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 1. " $${1\over 6}$$"
Q: A certain number of men can do a work in 60 days. If there were eight more men, it could be completed in 10 days less. How many men were there in the beginning?
465 06401e241a9f6c7de51a58a9a
6401e241a9f6c7de51a58a9a- 170false
- 255false
- 345false
- 440true
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 4. "40"
Q: 12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?
343 06401e28a86fd4161466d6a03
6401e28a86fd4161466d6a03- 1192true
- 2190false
- 3180false
- 4144false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 1. "192"
Q: 10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days?
441 06401e1bacbcfaac053031224
6401e1bacbcfaac053031224- 16 hrs /daytrue
- 210 hrs / dayfalse
- 312 hrs / dayfalse
- 415 hrs / dayfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 1. "6 hrs /day "
Q: A and B can do a piece of work in 12 days. B and C in 15 days and C and A in 20 days. If A, B and C work together, they will completer the work in : 1160 05cf0f1db0b8bee0fb6178ad9
5cf0f1db0b8bee0fb6178ad9- 15 daysfalse
- 2$$ 7{5\over 6} \ days$$false
- 310 daystrue
- 4$$ 15 {2\over 3} \ days$$false
- Show AnswerHide Answer
- Workspace
- SingleChoice