Time and Work Short Tricks Solved Problems for Competitive Exams
Time and Work is an important topic in the Quantitative Aptitude section for Bank and SSC Exam. In this topic, 2 to 3 questions are asked every year in competition exam. You should learn the shortcut tricks for saving time in the competitive exams.
Here is a detailed introduction of Time and Work along with short tricks which will help the candidates to prepare the topic well. For more practice, you can visit on Time and work problems with solutions.
Here you can get all the topics of Time and Work Aptitude by click here.
What is Time and work?
Performing or doing any work involves efforts of person over a period of time. Therefore, the number of person (P), the quantity of work (W) and the period of time taken (T) are important variables in problem-related to time and work.
Time and Work Short Tricks Solved Problems
Example 1: Chandni and Divakar can do a piece of work in 9 days and 12 days, respectively. If they work for a day alternatively, Chandni beginning in how many days, the work will be completed?
(A)
(B)
(C) 11.11
(D) 10
Solution
. Chandni’s 1 days’s work = 1/9.
Divakar’s 1 day’s work = 1/12.
Chandni and Divakar’s (1+1) = 2.
Day’s work = (1/9)+(1/12) = 7/36
So, in 10 days they do = (7×5)/36 = 35/36.
So, the remaining 1/36 {= 1-35/36}
Work will be done by Chandni
= (1/36)/(1/9) = 1/4.
Thus, total number of required days
= 10+(1/4) = days
Short Tricks
Efficiency of Chandni = 11.11%
Efficiency of Divakar = 8.33%
They do 19.44% work in 2 days.
⸫ They need 10 days to do 97.22% work.
Now, the rest work (2.78) was done by Chandni in 2.78/11.11 = 1/4 day
Therefore, total number of days
Required = 10+1/4 =
Example 2: Pipe A can fill an empty tank in 30 h while B can fill it in 45 h. Pipe A and B are opened and closed alternatively i.e., first pipe A is opened, then B, again A and then B and so on for 1 h each time without any time lapse. In how many hours the tank will be filled when it was empty, initially?
(A) 36
(B) 54
(C) 48
(D) 60
Solution
In 1 h pipe A can fill = 1/30 part of the tank
In 1 h pipe B can fill = 1/45 part of the tank
In 2 h pipes A and B can fill = 1/18 part of the tank
Therefore, in 36 h the tank will be completely filled.
Short Tricks
Efficiency of pipe A = 3.33%
Efficiency of pipe B = 2.22%
And combined efficiency = 5.55%
Therefore, in 2 h pipes A and B fill 5.55%. Thus, to fill 100% tank, these pipes will take 36 h.
Example 3: If 20 persons can do a piece of work in 7 days, then calculate the number of persons required to complete the work in 28 days.
(A) 5
(B) 10
(C) 15
(D) 25
Solution
Number of persons × days = work.
20 × 7 = 140 man-days.
Now, X × 28 = 140 man-days.
→ X = 5
Therefore, in second case the required number of person is 5.
Short Tricks
Since, work in constant, therefore
M1×D1 = M2×D2 = Work done
20 × 7 = M2 × 28 → M2 = 5.
Example 4: A can do a piece of work in 14 days, while B can do it in 21 days. In how many days, working together they will complete the whole work?
(A) 10.5
(B) 8
(C) 8.4
(D) 9
Solution
Efficiency of A = 7.14%
Efficiency of B = 4.76%
Efficiency of (A+B) = 11.9%
⸫ Number of days required by A and B, working together = 100/11.9 = 8.4 days
Hint you can see, that there is only one option between 8 and 9, which is 8.4.
For 8 days denominator should be 12.5 as for 9 days denominator should be almost 11.
Short Trick
1 days work of A and B = 1/14 + 1/21 = 5/42
⸫ Required number of days = 42/5 = 8.4 days.
Ask me in the comment section, if you face any problem while solving important Time and Work questions. Visit next page for more Time and Work problems.